A bunch of oil shippers is asking the Canada Vitality Regulator to compel the corporate behind the Trans Mountain pipeline growth to offer them with a full and detailed breakdown of the undertaking’s escalating building prices.
The shippers — which incorporates Canadian Pure Sources Ltd., Suncor Vitality Inc.,, Cenovus Vitality Inc., PetroChina Canada Ltd. and Marathon Petroleum Canada — are in search of an order from the regulator requiring Trans Mountain Corp. to offer extra details about why the undertaking’s prices have ballooned to greater than $30 billion from a 2017 estimate of $7.4 billion.
“The stakes are excessive: billions of {dollars} at subject, with Trans Mountain’s (prices) having greater than quintupled since 2017 — and its prices are nonetheless rising by billions, seemingly unchecked,” the oil firms said in a movement filed with the Canada Vitality Regulator earlier this week.
“But Trans Mountain refused to reply most of taking part shippers’ (request for data) and inappropriately dismissed most requests as irrelevant ‘fishing expeditions.’ ”
The Trans Mountain pipeline, which was purchased by the federal authorities in 2018, is Canada’s solely oil pipeline to the West Coast. Its practically full growth undertaking will enhance the pipeline’s capability by 590,000 barrels per day to a complete of 890,000 barrels per day, enhancing entry to export markets for Canadian oil firms.
However Trans Mountain Corp. and its oil firm prospects are at the moment engaged in a dispute over tolls, the time period for the charges the pipeline firm will cost to ship oil on the expanded pipeline.
In its most up-to-date replace supplied final month, Trans Mountain mentioned it now has motive to imagine the prices of the undertaking will are available in roughly $3.1 billion greater than the $30.9 billion estimate in Could 2023. It mentioned a ultimate tally received’t be obtainable till after the undertaking’s completion, anticipated someday this spring.
Oil firms are involved with the escalating prices as a result of they must pay for a portion of them within the type of rising tolls.
Whereas roughly 70 per cent of the undertaking’s price overruns will probably be borne by Trans Mountain, the remaining third — greater than $9 billion — is taken into account “uncapped prices” which enhance tolls in accordance with a method agreed to by shippers and authorised by the regulator greater than a decade in the past.
However the oil shippers say the brand new benchmark toll Trans Mountain needs to cost is sort of twice the quantity of a 2017 estimate, and say extra data should be supplied with the intention to show the rising price ticket of the undertaking is each cheap and mandatory.
They are saying they’ve requested Trans Mountain to offer a extra detailed breakdown, and are in search of an order from the regulator as a result of they aren’t happy with the corporate’s response.
The Canada Vitality Regulator has already granted approval for Trans Mountain to cost the upper toll on an interim foundation, however is but to make a ultimate resolution.
For its half, Trans Mountain Corp. — which is a Crown company — has mentioned 70 per cent of the undertaking’s price overruns will probably be borne by the pipeline firm and may have no impact on tolls.
The corporate has additionally beforehand said that due to the undertaking’s price overruns, it expects solely “modest returns” on its funding within the first few years of the expanded pipeline’s operation. It says that any toll stage under what Trans Mountain has utilized for “might affect Trans Mountain’s means to fulfill its monetary obligations.”
In December, Trans Mountain Corp. submitted written proof to the regulator during which it mentioned the pipeline growth undertaking has been affected by “extraordinary” components that embrace evolving compliance necessities, Indigenous lodging, stakeholder engagement and compensation necessities, excessive climate and the COVID-19 pandemic.
The corporate mentioned in its submitting that the undertaking’s price overruns have been “moderately and justifiably incurred.”
Building on the Trans Mountain pipeline growth undertaking started in 2019.